Business

Reliance coal gasification in Eluru: Rs 43,000 crore plan hinges on pilot

By Siddharth VermaBusiness Correspondent, Peepals Bharat
WhatsAppX
Representative image: coal mine excavation site

Representative image: Tyna_Janoch / Pixabay

Reliance plans a Rs 43,000 crore underground coal gasification complex in Eluru, Andhra Pradesh, reports said on 12 November; only a Rs 3,000 crore pilot is firm.

What Happened

Reliance Industries plans to invest about Rs 43,000 crore in an underground coal gasification complex in Eluru district of Andhra Pradesh, according to reports published on Thursday, 12 November 2026 that cite a draft agreement with the state government. The project would use the Chintalapudi and Recherla coal blocks, which the company won in coal ministry auctions, and would be built in two phases. The company did not immediately comment on the reports, so the figures come from government documents and reporting rather than from Reliance itself.

Reliance coal gasification: key facts

  • Planned investment: about Rs 43,000 crore (about $4.6 billion), in two phases.
  • Phase 1: about Rs 3,000 crore for exploration, geological studies and pilot demonstrations.
  • Phase 2: about Rs 40,000 crore initially, only if phase 1 succeeds and regulatory approvals are received.
  • Location: Chintalapudi and Recherla coal blocks in Eluru district, with estimated reserves of 3.13 billion tonnes of coal.
  • Jobs: about 5,000 direct and 35,000 indirect jobs, according to the reports.
  • Lifetime investment potential: up to Rs 2.7 trillion (Rs 2.7 lakh crore), according to one report.
  • Reports differ on status: one says a memorandum of understanding was signed, another describes a draft agreement.

Reliance coal gasification: why it matters

Underground coal gasification is a way of using coal without mining it. Instead of digging the coal out, air or oxygen and steam are sent down wells into the coal seam, where the coal is partly burned under control and turned into a gas mixture, often called syngas. That gas is brought to the surface and can be used to make power, fertiliser, chemicals or fuels. The method can open up coal that is too deep or too costly to mine in the usual way, but it is technically difficult and has to be watched closely for groundwater pollution and ground subsidence.

The two Eluru blocks were won through the coal ministry's auctions, and their estimated 3.13 billion tonnes of coal is what makes a project of this size possible. Turning even part of that coal into gas underground, rather than mining it and gasifying it in surface plants, would be a large industrial test of the method in India.

For Andhra Pradesh, the plan adds to a series of large investment announcements around the CII Partnership Summit in Visakhapatnam this week. Kia's planned second plant and ReNew's clean-energy commitments were announced in the same week, and the Reliance plan, if confirmed, would sit among the largest of them.

The two-phase structure is the key detail. Only the Rs 3,000 crore first phase is a firm plan for now. The much larger second phase depends on the pilot working and on approvals, so the Rs 43,000 crore figure is a ceiling for the first stage of the project, not money already committed.

Peepals calculation: the first phase is about 7% of the planned Rs 43,000 crore (3,000 ÷ 43,000 ≈ 0.07), so roughly 93% of the money depends on the pilot's success. The full Rs 43,000 crore works out to about Rs 8.6 crore per direct job (43,000 ÷ 5,000), or a little over Rs 1 crore per job if indirect jobs are counted too (43,000 ÷ 40,000 ≈ 1.08). The Rs 2.7 lakh crore lifetime figure is about 6.3 times the initial plan (2,70,000 ÷ 43,000 ≈ 6.3). Our calculation from the reported figures.

PhaseInvestmentWhat it covers
Phase 1about Rs 3,000 croreExploration, geological studies, pilot demonstrations
Phase 2about Rs 40,000 crore (initial)Full complex, only after phase 1 succeeds and approvals
Lifetime potentialup to Rs 2.7 lakh croreOver the project's life, according to one report

Impact

Short-term: the first visible work, if the agreement is finalised, will be exploration and pilot wells at the two blocks. Local land, water and environmental approvals will decide how quickly that starts.

Long-term: if the pilot works, the complex could supply gas for power, chemicals and fertilisers from Indian coal, reducing some imports, and create the jobs the reports mention. If it does not, the second phase will not go ahead.

Who is affected: residents and farmers around the Chintalapudi and Recherla blocks in Eluru district; job seekers in coastal Andhra Pradesh; the state government, which is courting large investments; and industries that buy gas, fertiliser and chemical inputs.

Key Takeaway

Reliance's reported Rs 43,000 crore underground coal gasification plan for Eluru district hinges on a Rs 3,000 crore pilot phase; the rest goes ahead only if that pilot works and approvals follow.

Questions and Answers

What is Reliance's coal gasification project in Andhra Pradesh?

According to reports on 12 November 2026, Reliance Industries plans an underground coal gasification complex worth about Rs 43,000 crore at the Chintalapudi and Recherla coal blocks in Eluru district, built in two phases.

What is underground coal gasification?

It is a method of turning coal into gas inside the seam, without mining it. Air or oxygen and steam are pumped into the coal through wells, and the gas produced is brought up and used for power, fertiliser, chemicals or fuels.

How many jobs will the Reliance Eluru project create?

The reports put the figure at about 5,000 direct and 35,000 indirect jobs, though these depend on the full project going ahead.

Has Reliance confirmed the Rs 43,000 crore investment?

Not publicly. The figures come from government documents and reports of a draft agreement, and Reliance did not immediately comment.

Disclaimer: Prepared by the Peepals newsroom from publicly available sources with AI assistance. Information is accurate to the best of our knowledge at the time of publication and may change. Images may be representative. Not professional advice. Report an error via our contact page.

#Reliance coal gasification#underground coal gasification#Eluru#Andhra Pradesh investment#Chintalapudi coal block

By Siddharth Verma, Business CorrespondentCovers Business and more for Peepals Bharat. All stories by Siddharth Verma

Get the day's stories in your inbox

Peepals Weekly: the week decoded, free. One email a week, unsubscribe in one click.

Siddharth Verma is a pen name of the Peepals Global Editorial Team, which researches, fact-checks and publishes every story. The portrait is an illustration.

Responsible for this story: the Peepals Global Editorial Team, led by editor Prashant Sonar. How we report

More from Peepals Bharat

The week's top stories, in your inbox. Free.

The most important, fact-checked stories from all seven publications, once a week.